WHAT’S HAPPENING?
Last weekend, chiller plant work was conducted that affected KACB.  This weekend, Campus Facilities must perform major chiller plant work on the Holland Chiller Plant.  This will affect CCB comfort cooling and TSO's 247, HPCF, and 312 data centers.


WHEN IS IT HAPPENING?
The maintenance window is expected to begin at 8:00 PM on Friday, January 22 , and run through 6:00 AM, Monday, January 25, 2016.  TSO will begin shutting down servers at 7:00 PM, January 22, and expects to have all services restored approximately 3 hours after the chiller plant comes back online.


WHY IS IT HAPPENING?
Campus Facilities must perform major chiller plant work on the Holland Chiller Plant.  Due to the reduced chilled water capacity, TSO must shut down non-critical servers in CCB 247, HPCF, and 312 data centers.


WHO IS AFFECTED?
Occupants of CCB offices and lab space.  Users of the following servers and websites:


Affected websites:
coweb.cc.gatech.edu
salinn.cc.gatech.edu
swiki.cc.gatech.edu

Affected servers:
aspidiske.cc.gatech.edu
atlas.cc.gatech.edu
bear.cc.gatech.edu
can.cc.gatech.edu
canopus.cc.gatech.edu
compbio.cc.gatech.edu
dice.cc.gatech.edu
dragonfly.cc.gatech.edu
factor cluster
gallinago.cc.gatech.edu
grizzly.cc.gatech.edu
hadar.cc.gatech.edu
half of the jedi cluster
half of the Jinx cluster
hangiri.cc.gatech.edu
helios.cc.gatech.edu
house.cc.gatech.edu
hpclab.cc.gatech.edu
hpclab-storage-1.cc.gatech.edu
ion cluster
killerbees
know.cc.gatech.edu
mirasol.cc.gatech.edu
nitro1.cc.gatech.edu
nitro2.cc.gatech.edu
no.cc.gatech.edu
pasta cluster
pele.cc.gatech.edu
peppered.cc.gatech.edu
pequin.cc.gatech.edu
perseus.cc.gatech.edu
plenko.cc.gatech.edu
polymoa cluster
psum09.cc.gatech.edu
ra.cc.gatech.edu
serrano.cc.gatech.edu
silwa.cc.gatech.edu
stream2.cc.gatech.edu
swallowtail.cc.gatech.edu
swallowtail2.cc.gatech.edu
vogue cluster
waxy.cc.gatech.edu
woolybear cluster


WHAT DO YOU NEED TO DO?
CCB occupants should shut down their non-essential systems before leaving for the day on Friday.  


WHO SHOULD YOU CONTACT FOR QUESTIONS?
TSO Help Desk (CCB 148, 404.894.7065, helpdesk@cc.gatech.edu).


UPDATE:
Due to the early closing of campus today, Campus Facilities has decided to move up the chiller plant work.  As such, TSO will begin shutting down machines at 11:00 AM, January 22, 2016.  TSO was unable to get Campus Facilities to reschedule and apologizes for any inconvenience.


UPDATE:
The chiller plant maintenance was completed early.  TSO restarted most of the affected servers by 6:30 PM, Sunday, January 24, 2016.

Owner of Alert